1.7 KiB
1.7 KiB
1 | ID | Date | EventName |
---|---|---|---|
2 | R1-1 | 1 | Lawyer Review |
3 | R1-1 | 2 | Fill out application |
4 | R2-1 | 1 | Fill out application |
5 | R2-1 | 2 | Lawyer Review |
6 | R2-1 | 3 | Architect Review |
7 | R2-2 | 1 | Fill out application |
8 | R2-2 | 2 | Architect Review |
9 | R2-2 | 3 | Lawyer Review |
10 | R3-1 | 1 | Fill out application |
11 | R3-1 | 2 | Architect Review |
12 | R3-1 | 3 | Reject |
13 | R3-2 | 1 | Fill out application |
14 | R3-2 | 2 | Architect Review |
15 | R3-2 | 3 | Reject |
16 | R3-2 | 4 | Applicant informed |
17 | R3-3 | 1 | Fill out application |
18 | R3-3 | 2 | Architect Review |
19 | R3-3 | 3 | Reject |
20 | R3-3 | 4 | Change phase to abort |
21 | R3-4 | 1 | Fill out application |
22 | R3-4 | 2 | Architect Review |
23 | R3-4 | 3 | Reject |
24 | R3-4 | 4 | Change phase to abort |
25 | R3-4 | 5 | Applicant informed |
26 | R4-1 | 1 | Fill out application |
27 | R4-1 | 2 | Architect Review |
28 | R4-1 | 3 | First payment |
29 | R4-2 | 1 | Fill out application |
30 | R4-2 | 2 | Architect Review |
31 | R4-2 | 3 | First payment |
32 | R4-2 | 4 | First payment |
33 | R4-3 | 1 | Fill out application |
34 | R4-3 | 2 | Architect Review |
35 | R4-3 | 3 | First payment |
36 | R4-3 | 3 | Undo payment |
37 | R4-3 | 5 | First payment |
38 | R5-1 | 1 | Fill out application |
39 | R5-1 | 2 | Architect Review |
40 | R5-1 | 3 | Account no. changed |
41 | R5-2 | 1 | Fill out application |
42 | R5-2 | 2 | Architect Review |
43 | R5-2 | 3 | Account no. changed |
44 | R5-2 | 4 | First payment |
45 | R5-3 | 1 | Fill out application |
46 | R5-3 | 2 | Architect Review |
47 | R5-3 | 3 | Account no. changed |
48 | R5-3 | 4 | Approve change |
49 | R5-3 | 5 | First payment |
50 | R6-1 | 1 | Fill out application |
51 | R6-1 | 2 | Architect Review |
52 | R6-1 | 3 | Change phase to payout |
53 | R6-2 | 1 | Fill out application |
54 | R6-2 | 2 | Architect Review |
55 | R6-2 | 3 | Change phase to payout |
56 | R6-2 | 4 | First payment |
57 | R7-1 | 1 | Fill out application |
58 | R7-1 | 2 | Architect Review |
59 | R7-1 | 3 | Change phase to payout |
60 | R7-1 | 4 | Change phase to end report |
61 | R7-2 | 1 | Fill out application |
62 | R7-2 | 2 | Architect Review |
63 | R7-2 | 3 | Change phase to payout |
64 | R7-2 | 4 | First payment |
65 | R7-2 | 5 | Change phase to end report |
66 | R8-1 | 1 | Fill out application |
67 | R8-1 | 2 | Execute abandon |
68 | R8-1 | 3 | Architect Review |
69 | R8-2 | 1 | Fill out application |
70 | R8-2 | 2 | Execute abandon |
71 | R8-2 | 3 | Change phase to abandon |